A year of works is about to begin on Falmouth’s Bickland Water Road
If you use Bickland Water Road, the next twelve months are going to look different. Temporary traffic lights, a wider path and a string of new crossings are all on the way, and the work starts early next month.
Cormac says the active travel improvements are meant to make the area safer and easier to use for people walking and cycling. The plan is a continuous, wider path along the eastern side of the road, running past homes, businesses and local schools in Falmouth.
Your daily dose of Cornwall
News, events and goings on across the Duchy
What’s changing on Bickland Water Road
The existing footway will be widened to three metres where possible, so pedestrians and cyclists can share it.
Four new signal-controlled crossings will link residential areas, businesses and local schools. Junctions will be narrowed to shorten crossing distances and slow traffic down, and detailed drawings for the scheme show several side roads getting cycle priority crossings on raised tables.
The work also includes new kerbing, electrical ducting, resurfacing and road markings. New streetlighting and some seating areas are part of it too.
What it means for your journey
Work will happen in the daytime under temporary traffic lights. At peak times the lights will be operated manually to keep traffic moving.
Cormac expects delays, so allow extra time for your journeys.
The resurfacing comes towards the end of the project. It needs a series of road closures, so it will be done at night with diversion routes in place.
If you park along the road, it’s worth knowing the plans extend the ‘no waiting at any time’ restrictions in two places, by 15 metres and 37 metres.
The route, section by section
The works will move along the road in seven stages, each with its own set of drawings.
Your daily dose of Cornwall
News, events and goings on across the Duchy
Union Corner roundabout to Levant Rise roundabout
The footway gets wider and the streetlighting moves. A new toucan crossing, where people on foot and on bikes can cross together, goes in on the approach to the Levant Rise roundabout near Conway Road. Two existing pedestrian crossings and their traffic islands are marked for removal, while an existing uncontrolled crossing by the roundabout stays.
Levant Rise roundabout to Bickland Business Centre
A new footway goes in on the verge. By Bickland Park football ground, the existing pedestrian island is replaced with a toucan crossing. The plans note extensive vegetation trimming along the southern side of the road to keep it wide enough for lorries. At the Bickland Business Centre junction, the mouth of the junction is narrowed to slow vehicles turning in, with a cycle priority crossing on a raised table.
Bickland junction to Empire Way
The footway is widened, the streetlighting relocated and the layby shortened. The Empire Way junction is narrowed in the same way, with its own cycle priority crossing on a raised table.
Your daily dose of Cornwall
News, events and goings on across the Duchy
Empire Way to Watson Marlow
Controlled pedestrian crossing points go in and the footway gets wider. On this stretch the carriageway itself is narrowed to make room for a three-metre shared path, and the junction widths stay as they are for lorry access. The plans also extend the ‘no waiting at any time’ parking restrictions by 15 metres.
Watson Marlow to St Francis Primary School
More footway widening and new pedestrian-controlled crossings. An existing toucan crossing is upgraded to meet current standards, and the Mongleath Road junction is narrowed, with a set-back cycle priority crossing on a raised table.
St Francis Primary School to Falmouth Business Park
The footway is widened and new street lighting installed. The ‘no waiting at any time’ restrictions here are extended by 37 metres, and a side road junction gets the narrower mouth and raised cycle priority crossing treatment.
Your daily dose of Cornwall
News, events and goings on across the Duchy
Falmouth Business Park to Bosmeor Road and Prislow Lane
The footway is widened and ducting laid for new street lighting. The plans for this last stretch run on to Prislow Lane, with the junctions at Bosmeor Road and Prislow Lane both narrowed and their kerbs tightened to slow vehicles turning in.
After that, another 270m of electrical ducting will go in for the new streetlight columns, and the newly widened footways will be resurfaced.
Questions about the works
Cormac says it will post updates on its project page as the works progress. You can also contact the team on 0300 1234 222 or email [email protected].
“Thank you in advance for your cooperation, we are very grateful to everyone for their support and patience,” Cormac said.
Read Next
- St IvesFor anyone arriving in St Ives by bus or train, the first real look at the bay comes from the Malakoff.
Share This Story, Choose Your Platform!
To keep up with the latest cornish news follow us below
Follow CornishStuff on Facebook - Like our Facebook page to get the latest news in your feed and join in the discussions in the comments. Click here to give us a like!
Follow us on Twitter - For the latest breaking news in Cornwall and the latest stories, click here to follow CornishStuff on X.
Follow us on Instagram - We also put the latest news in our Instagram Stories. Click here to follow CornishStuff on Instagram.
- 1
- 2
- 3
- 4
- 5
- 6